Overhead cranes—often called bridge cranes—are the quiet workhorses that keep heavy industry moving. This field-tested breakdown shows how a full overhead crane system comes to life inside a structural building. We’ll cover final load testing and handover—with the same checklists pro installers use.
What an Overhead/Bridge Crane Is
At heart, a bridge crane is a bridge beam that spans between two runway beams, carrying a trolley-mounted hoist for precise, vertical picks. The result is smooth X-Y-Z motion: cross-travel along the bridge.
You’ll find them in fabrication bays, steel plants, power stations, oil & gas shops, precast yards, and logistics hubs.
Why they matter:
Controlled moves for large, expensive equipment.
Huge efficiency gains.
Lower risk during rigging, lifting, and transport inside facilities.
Support for pipelines, structural steel, and big machinery installs.
System Components We’re Installing
Runways & rails: continuous beams and rail caps.
End trucks: motorized gearboxes for long-travel.
Bridge girder(s): single- or double-girder configuration.
Trolley & hoist: cross-travel carriage with lifting unit.
Electrics & controls: power supply, festoon or conductor bars.
Stops, bumpers & safety: overload protection, e-stops.
Depending on capacity and span, the crane might be a single-girder 10-ton unit or a massive double-girder 100-ton system. The choreography is similar, but the scale, lift plans, and checks grow with the tonnage.
Pre-Install Prep
Good installs start on paper. Key steps:
Drawings & submittals: Approve general arrangement (GA), electrical schematics, and loads to the structure.
Permits/JSAs: Job Safety Analysis (JSA) for each lift step.
Runway verification: Survey columns and runway beams for straightness, elevation, and span.
Power readiness: Confirm conductor bars or festoon supports, cable trays, and isolation points.
Staging & laydown: Lay out slings, shackles, spreader bars, and chokers per rigging plan.
People & design builder roles: Brief everyone on radio calls and stop-work authority.
Millimeters at the runway become centimeters at full span. Spend time here.
Getting the Path Right
If rails are off, nothing else will run true. Targets and checks:
Straightness & elevation: shim packs under clips to meet tolerance.
Gauge (span) & squareness: Check centerlines at intervals; confirm end squareness and expansion joints.
End stops & buffers: Install and torque per spec.
Conductor system: Mount conductor bars or festoon track parallel to the rail.
Record as-built readings. Correct now or pay later in wheel wear and motor overloads.
Putting the Span in the Air
Rigging plan: Softeners protect painted flanges. Taglines for swing control.
Sequence:
Lift end trucks to runway level and set temporarily on blocks.
For double-girder cranes, lift both girders with a matched raise.
Use drift pins to align flange holes; torque to spec.
Verify camber and bridge square.
Before anyone celebrates, bump-test long-travel motors with temporary power (under permit): confirm limit switch wiring. Lock out after test.
The Heart of the Lift
Trolley installation: Mount wheels, align wheel flanges, set side-clearances.
Hoist reeving: Lubricate wire rope; verify dead-end terminations.
Limits & load devices: Check overload/SLI and emergency stop.
Cross-travel adjustment: Align trolley rails on a double-girder.
Pendant/remote: Install pendant festoon or pair radio receiver; function-test deadman and two-step speed controls.
Grinding noises mean something’s off—stop and inspect. Don’t mask issues with higher VFD ramps.
Electrics & Controls
Power supply: Conductor bars with collectors or a festoon system.
Drive setup: Enable S-curve profiles for precise positioning.
Interlocks & safety: E-stops, limit switches, anti-collision (if multiple cranes), horn, beacon.
Cable management: Secure junction boxes; label everything for maintenance.
Commissioning crews love clean labeling and clear folders. If it isn’t documented, it didn’t happen—put it in the databook.
Trust but Verify
Inspection Test Plan (ITP): Third-party witness for critical steps.
Torque logs: Re-check after 24 hours if required.
Level & gauge reports: Note any corrective shims.
Motor rotation & phasing: Document bump tests.
Functional tests: Anti-collisions and zone interlocks.
A tidy databook speeds client acceptance.
Load Testing & Commissioning
Static load test: Hold at mid-span and near end stops; monitor deflection and brake performance.
Dynamic load test: Check sway, braking distances, and VFD fault logs.
Operational checks: Emergency stop shuts down all motions.
Training & handover: Operator basics, daily pre-use checks, rigging do’s & don’ts.
Only after these pass do you hand over the keys.
Where These Cranes Shine
Construction & steel erection: placing beams, trusses, and precast.
Oil & gas & power: generator and turbine assembly.
Steel mills & foundries: large part transfer.
Warehousing & logistics: high throughput lanes.
Floor stays clear, production keeps flowing, and precision goes up.
Do It Safe or Don’t Do It
Rigging discipline: rated slings & shackles, correct angles, spreader bars for load geometry.
Lockout/Tagout: test before touch every time.
Fall protection & edges: scissor lifts and manlifts inspected.
Runway integrity: no cracked welds, correct bolt grades, proper grout.
Duty class selection: match crane class to cycles and loads.
A perfect lift is the one nobody notices because nothing went wrong.
Troubleshooting & Pro Tips
Crab angle/drift: verify end-truck wheel diameters and gearbox mounts.
Hot gearboxes: adjust brake air gap and reduce VFD decel.
Rope drum spooling: check fleet angle and sheave alignment.
Pendant lag or dropout: shield noisy VFD cables.
Wheel wear & rail pitting: lubrication and alignment issues.
A 10-minute weekly check saves days of downtime later.
FAQ Snippets
Overhead vs. gantry? Choose per site constraints.
Single vs. double girder? Span and duty class usually decide.
How long does install take? Scope, bay readiness, and tonnage rule the schedule.
What’s the duty class? FEM/ISO or CMAA classes define cycles and service—don’t guess; size it right.
Why Watch/Read This
If you’re a civil or mechanical engineer, construction manager, shop supervisor, or just a mega-project fan, this deep dive makes the whole process tangible. You’ll gain a checklist mindset that keeps cranes safe and productive.
Need a field bundle with JSA templates, rigging calculators, and commissioning sheets?
Get the toolkit now and cut hours from setup while boosting safety and QA/QC. Save it to your site tablet for quick reference.
...